ApprovedScheduledIn ProgressPunch ListCompleteInvoiced
Field progress
100%
Due Aug 12, 2026
Hours actual / est.
36 / 38
-2 hrs variance
Cost to date
$4,870
Budget $5,100
Projected profit
$3,730
43.4% of contract
Labor log
Actual man-hours recorded against this project
Estimated hours consumed95%
- No hours logged yet.
Inventory allocation
Committed at approval, adjusted for field usage
| Item | Committed | Used | Variance |
|---|---|---|---|
| Natural bluestone patio, 1.5" thermal, sand-set | 860 sq ft | 863 sq ft | +3 damaged/replaced |
| Modular fire feature with gas line stub | 1 each | 1 each | On plan |
| Serviceberry, multi-stem, 8-10′ | 6 each | 6 each | On plan |
Purchase orders
Vendor commitments tied to this project
- No purchase orders yet.
Field update
Available to the assigned foreman
Project facts
- Stage
- Invoiced
- Health
- On track
- Foreman
- Dean Kowalski
- Crew
- 2 people
- Start
- Aug 4, 2026
- Target end
- Aug 12, 2026
- Contract value
- $8,600
- Payment
- Paid
- QuickBooks
- QB-10490
Approved estimate
Emerald Green Arborvitae 6-7' B&B is the primary allocated item on this job.